TUKE'H BEN'LAY RESETTLEMENT AND HOUSING PROJECT (IMPROVEMENT AND UPGRADING OF 100 UNITS RESETTLEMENT AND IP HOUSING)

Batian, Maitum, Sarangani Province

Project Progress

Actual Progress
100.0%
  • Project Billboard / Signboard0.58% / 0.58%Complete
  • Mobilization / Demobilization1.28% / 1.28%Complete
  • Masonry Works5.71% / 5.71%Complete
  • Carpentry Works7.24% / 7.24%Complete
  • Painting Works85.19% / 85.19%Complete
As of June 13, 2025
Completed

Projected accomplishment: 100.0% · Slippage: 0.0%

Project ID
1208005-BATIAN-2025-0001
Date Started
March 29, 2025
Target Completion
June 13, 2025
Project Duration
77 calendar days

Project Overview

Repair and painting of 100 housing units.

Project Type: Road

Batian, Maitum, Sarangani Province

Cost and Funding

Funding Source
20% LDF 2025
Total Estimated Project Cost
₱1,096,791.42

Progress Updates

As of
100.0%
  • Project Billboard / Signboard0.58% / 0.58%Complete
  • Mobilization / Demobilization1.28% / 1.28%Complete
  • Masonry Works5.71% / 5.71%Complete
  • Carpentry Works7.24% / 7.24%Complete
  • Painting Works85.19% / 85.19%Complete
Posted by: Jubileah PasatiempoDate Posted: November 3, 2026Edited by Jubileah Pasatiempo · November 5, 2026

Completed last July 11, 2025.

Projected Accomplishment: 100.0%Accomplishment to Date: 100.0%Slippage: 0.0%

TUKE'H BEN'LAY RESETTLEMENT AND HOUSING PROJECT (IMPROVEMENT AND UPGRADING OF 100 UNITS RESETTLEMENT AND IP HOUSING) project update photo