CONSTRUCTION OF KALAONG FARM-TO-MARKET ROAD

Kalaong, Maitum, Sarangani Province

Project Progress

Actual Progress
100.0%
  • Project Billboard / Signage0.53% / 0.53%Complete
  • Occupational Safety and Health Program2.73% / 2.73%Complete
  • Traffic Management4.49% / 4.49%Complete
  • Mobilization / Demobilization9.48% / 9.48%Complete
  • Surplus Common Excavation1.03% / 1.03%Complete
  • Embankment from Roadway / Structure Excavation (Common Soil)1.90% / 1.90%Complete
  • Subgrade Preparation (Common Material)0.95% / 0.95%Complete
  • Aggregate/Subbase Course15.80% / 15.80%Complete
  • Gravel Surface Course3.17% / 3.17%Complete
  • Portland Cement Concrete Pavement (Unreinforced) - 0.23m thk.59.92% / 59.92%Complete
As of April 16, 2026
Completed

Projected accomplishment: 100.0% · Slippage: 0.0%

Project ID
1208005-KALAONG-2026-0001
Date Started
January 16, 2026
Target Completion
April 16, 2026
Project Duration
91 calendar days

Project Overview

Concreting of 0.205 lnm road.

Project Type: Road

Kalaong, Maitum, Sarangani Province

Cost and Funding

Funding Source
LGSF-SBDP 2025
Total Estimated Project Cost
₱2,494,824.89

Progress Updates

As of
100.0%
  • Project Billboard / Signage0.53% / 0.53%Complete
  • Occupational Safety and Health Program2.73% / 2.73%Complete
  • Traffic Management4.49% / 4.49%Complete
  • Mobilization / Demobilization9.48% / 9.48%Complete
  • Surplus Common Excavation1.03% / 1.03%Complete
  • Embankment from Roadway / Structure Excavation (Common Soil)1.90% / 1.90%Complete
  • Subgrade Preparation (Common Material)0.95% / 0.95%Complete
  • Aggregate/Subbase Course15.80% / 15.80%Complete
  • Gravel Surface Course3.17% / 3.17%Complete
  • Portland Cement Concrete Pavement (Unreinforced) - 0.23m thk.59.92% / 59.92%Complete
Posted by: Jubileah PasatiempoDate Posted: November 4, 2026Edited by Jubileah Pasatiempo · November 5, 2026

Project Completed.

Projected Accomplishment: 100.0%Accomplishment to Date: 100.0%Slippage: 0.0%