CONSTRUCTION OF KALAONG FARM-TO-MARKET ROAD
Kalaong, Maitum, Sarangani Province
Project Progress
Actual ProgressAs of April 16, 2026
Completed100.0%
- Project Billboard / Signage0.53% / 0.53%Complete
- Occupational Safety and Health Program2.73% / 2.73%Complete
- Traffic Management4.49% / 4.49%Complete
- Mobilization / Demobilization9.48% / 9.48%Complete
- Surplus Common Excavation1.03% / 1.03%Complete
- Embankment from Roadway / Structure Excavation (Common Soil)1.90% / 1.90%Complete
- Subgrade Preparation (Common Material)0.95% / 0.95%Complete
- Aggregate/Subbase Course15.80% / 15.80%Complete
- Gravel Surface Course3.17% / 3.17%Complete
- Portland Cement Concrete Pavement (Unreinforced) - 0.23m thk.59.92% / 59.92%Complete
Projected accomplishment: 100.0% · Slippage: 0.0%
- Project ID
- 1208005-KALAONG-2026-0001
- Date Started
- January 16, 2026
- Target Completion
- April 16, 2026
- Project Duration
- 91 calendar days
Project Overview
Concreting of 0.205 lnm road.
Project Type: Road
Kalaong, Maitum, Sarangani Province
Cost and Funding
- Funding Source
- LGSF-SBDP 2025
- Total Estimated Project Cost
- ₱2,494,824.89