← Back to Project List

Construction of multi-purpose building (eccD) in barangay mabay

Mabay, Maitum, Sarangani Province

Project Progress

Actual Progress
100.0%
  • Permits and Clearances2.05% / 2.05%Complete
  • Project Billboard / Signage0.46% / 0.46%Complete
  • Occupational Safety and Health Program0.65% / 0.65%Complete
  • Mobilization / Demobilization1.30% / 1.30%Complete
  • Provision of Field Office for the Engineer (Rental Basis)1.00% / 1.00%Complete
  • Excavation, Common Soil1.24% / 1.24%Complete
  • Embankment1.47% / 1.47%Complete
  • Gravel Fill3.86% / 3.86%Complete
  • Reinforcing Steel (Deformed)13.15% / 13.15%Complete
  • Formworks & Falseworks9.15% / 9.15%Complete
  • Reinforced Concrete Works8.88% / 8.88%Complete
  • CHB Non Load Bearing (including reinforcements)6.70% / 6.70%Complete
  • Plumbing Works5.21% / 5.21%Complete
  • Wooden Doors and Windows3.52% / 3.52%Complete
  • Ceiling Panel2.91% / 2.91%Complete
  • Painting Works1.93% / 1.93%Complete
  • Structural Steel, Roof Framing21.90% / 21.90%Complete
  • Corrugated Metal Roofing3.38% / 3.38%Complete
  • Conduits, Boxes & Fittings (Conduit Works / Conduit Rough-ins)4.56% / 4.56%Complete
  • Fire Alarm Bell0.16% / 0.16%Complete
  • Water Tank (Rain Collector)0.65% / 0.65%Complete
  • Roll-up Ramp/ Leveling Pad5.86% / 5.86%Complete
As of February 14, 2026
On Track

Projected accomplishment: 100.0% · Slippage: 0.0%

Project ID
1208005-MABAY-2025-0001
Date Started
November 27, 2025
Target Completion
February 14, 2026
Project Duration
80 calendar days

Project Overview

Project Completed.

Project Type: Road

Mabay, Maitum, Sarangani Province

Cost and Funding

Funding Source
FY 2024 LGSF FALGU
Total Estimated Project Cost
₱1,994,972.10

Progress Updates

As of
100.0%
  • Permits and Clearances2.05% / 2.05%Complete
  • Project Billboard / Signage0.46% / 0.46%Complete
  • Occupational Safety and Health Program0.65% / 0.65%Complete
  • Mobilization / Demobilization1.30% / 1.30%Complete
  • Provision of Field Office for the Engineer (Rental Basis)1.00% / 1.00%Complete
  • Excavation, Common Soil1.24% / 1.24%Complete
  • Embankment1.47% / 1.47%Complete
  • Gravel Fill3.86% / 3.86%Complete
  • Reinforcing Steel (Deformed)13.15% / 13.15%Complete
  • Formworks & Falseworks9.15% / 9.15%Complete
  • Reinforced Concrete Works8.88% / 8.88%Complete
  • CHB Non Load Bearing (including reinforcements)6.70% / 6.70%Complete
  • Plumbing Works5.21% / 5.21%Complete
  • Wooden Doors and Windows3.52% / 3.52%Complete
  • Ceiling Panel2.91% / 2.91%Complete
  • Painting Works1.93% / 1.93%Complete
  • Structural Steel, Roof Framing21.90% / 21.90%Complete
  • Corrugated Metal Roofing3.38% / 3.38%Complete
  • Conduits, Boxes & Fittings (Conduit Works / Conduit Rough-ins)4.56% / 4.56%Complete
  • Fire Alarm Bell0.16% / 0.16%Complete
  • Water Tank (Rain Collector)0.65% / 0.65%Complete
  • Roll-up Ramp/ Leveling Pad5.86% / 5.86%Complete
Posted by: Jubileah PasatiempoDate Posted: November 5, 2026Edited by Jubileah Pasatiempo · November 5, 2026

Project Completed

Projected Accomplishment: 100.0%Accomplishment to Date: 100.0%Slippage: 0.0%

Construction of multi-purpose building (eccD) in barangay mabay project update photo