Construction of multi-purpose building (eccD) in barangay mabay
Mabay, Maitum, Sarangani Province
Project Progress
Actual ProgressAs of February 14, 2026
On Track100.0%
- Permits and Clearances2.05% / 2.05%Complete
- Project Billboard / Signage0.46% / 0.46%Complete
- Occupational Safety and Health Program0.65% / 0.65%Complete
- Mobilization / Demobilization1.30% / 1.30%Complete
- Provision of Field Office for the Engineer (Rental Basis)1.00% / 1.00%Complete
- Excavation, Common Soil1.24% / 1.24%Complete
- Embankment1.47% / 1.47%Complete
- Gravel Fill3.86% / 3.86%Complete
- Reinforcing Steel (Deformed)13.15% / 13.15%Complete
- Formworks & Falseworks9.15% / 9.15%Complete
- Reinforced Concrete Works8.88% / 8.88%Complete
- CHB Non Load Bearing (including reinforcements)6.70% / 6.70%Complete
- Plumbing Works5.21% / 5.21%Complete
- Wooden Doors and Windows3.52% / 3.52%Complete
- Ceiling Panel2.91% / 2.91%Complete
- Painting Works1.93% / 1.93%Complete
- Structural Steel, Roof Framing21.90% / 21.90%Complete
- Corrugated Metal Roofing3.38% / 3.38%Complete
- Conduits, Boxes & Fittings (Conduit Works / Conduit Rough-ins)4.56% / 4.56%Complete
- Fire Alarm Bell0.16% / 0.16%Complete
- Water Tank (Rain Collector)0.65% / 0.65%Complete
- Roll-up Ramp/ Leveling Pad5.86% / 5.86%Complete
Projected accomplishment: 100.0% · Slippage: 0.0%
- Project ID
- 1208005-MABAY-2025-0001
- Date Started
- November 27, 2025
- Target Completion
- February 14, 2026
- Project Duration
- 80 calendar days
Project Overview
Project Completed.
Project Type: Road
Mabay, Maitum, Sarangani Province
Cost and Funding
- Funding Source
- FY 2024 LGSF FALGU
- Total Estimated Project Cost
- ₱1,994,972.10





